HERE WE GO! LET THE CONSTRUCTION BEGIN!
You can expect to see the dirt flying now! Bach and Company of Clayton will be the prime contractor, working from plans by architect Mike Aubertine.

The front elevation is depicted at the top of this page. You can see the floor plan by clicking here.

Well, progress has been slow. Our members have a lot on their plates during the summer, and we're still waiting for an approval for our kitchen plan. But we're progressing. It's looking like a fall opening...

Pay us a visit from time to time and we'll let you know when we're confident that we can start booking events. We'd love to host yours!

You can see the early details and progress:

Use your browser's BACK button to return here
It's only a hole in the ground, but it's ours! (August 2)
The basement walls are progressing. The liteform walls for the basement are complete, with the rest to be of frame construction. (August 8)
The first walls are up! Three walls are up and sheathed. The roof can't be far behind.
Things are taking shape. The exterior walls are complete, except around the main entry. On the inside, the bathroom walls have been framed. The sidewalk along the front of the building has just been finished in this shot.
Looking more like a building. As you read this, the roof has been sheathed and is ready for shingles.

Here are a series of pictures taken in mid-October. Use your browser's back button to come back here. Front View
East End - Basement Access
West End
The interior isn't anywhere near done - and the pictures are a tad dark.
Main Hall
Through the Kitchen Door
Bar Area

Final Floor Plan
Basement - Old Version, but essentially the same (not scaled with other drawings)